Day-by-Day Log of Construction:
Last updated on November 14, 2004
| Date: | Description: | Calendar: |
| 7-22-02 | Signed contract to build and paid $1000 earnest money. |
![]() |
| 8-24-02 | Site surveyed and staked out* | |
| 8-26-02 | Foundation dug and primary forms installed. After measuring, we found the foundation to be 3' too far back. The trenches will have to be filled-in, tamped and redug. | |
| 9-03-02 | Primary forms removed and trenches back-filled. | |
| 9-10-02 | New foundation dug. | |
| 9-14-02 | Primary forms re-installed and additional trenching done for plumbing. | |
| 9-17-02 | PVC sewer lines installed | |
| 9-18-02 | Copper water lines installed. Plumbing rough-in complete. | |
| 9-23-02 | Plumbing buried and foundation back-filled. Rebar installed and footings prep'd for foundation mono-pour. | |
| 9-26-02 | Concrete slab poured!!! | |
| 9-27-02 | Unbelievable!!! The first floor is almost completely framed! | |
| 9-30-02 | 1st floor framing complete, trusses installed over 1st floor and garage. | |
| 10-1-02 | 2nd floor framing complete. | |
| 10-2-02 | All trusses up and roof mostly complete. | |
| 10-3-02 | All framing is complete and exterior door and windows are installed. | |
| 10-8-02 | Heating/Cooling rough-in complete. (pix to come) | |
| 10-14-02 | Electrical rough-in complete. | |
| 10-18-02 | Data-Comm rough-in complete. | |
| 10-24-02 | Asphalt shingle roof complete. | |
| 10-25-02 | Special AV/datacomm wiring installed. | |
| 10-31-02 | External wall insulation install complete. | |
| 11-1-02 | Rough grading of back yard complete and Exterior wall lathing and stucco prep started. | |
| Sheet rock, tape and texture complete | ||
| Vinyl flooring installed | ||
| 1st paint complete | ||
| Cabinets installed | ||
| Plumbing fixtures installed | ||
| 12-9-02 | Carpet install complete.* | |
| 12-10-02 | Landscaping complete in front of house and door lock installed. House locked for first time. | |
| 12-11-02 | Fencing and gates complete. | |